Shaker-deck wash plant

Wash plant feeder pulley jam

A rock locks the feeder tail pulley while the driven belt slips and smokes.

  • 2 h
  • Intermediate
  • 8 steps
  • 9 tools
Feed conveyor belt and tail cog pulley on a shaker-deck wash plant

The whole job 8 steps

Made by AI. A mechanic hasn't checked it line by line yet. Use it to plan the job, and follow the maker's manual for specs and procedures.

Safety first

Mechanic job

Do these before step 1.

  • DANGERLock out: implements down, chocked, key out, isolator off, tag on.
  • WARNINGHeavy part (23 kg+): lifting gear or two people, mind pinch points.
  • DANGERMovement: crib raised equipment and restrain the belt before release.
  • WARNINGHeat: let smoking rubber cool; keep fire equipment ready.

Stop and call a pro or the dealer if

  • Call MSI for structural cracks, bent shaft, damaged cogs or an uncertain isolation method.

Mechy's guides help, but they don't replace the maker's manual, your training or your site's rules. If something doesn't match what you see, stop and check.

Tools

Tick what you have. In the app, Mechy ticks the ones it can see in your photos.

Parts and supplies

  • 1×Feeder belt, if heat damagedMatch MSI serial-specific belt construction and spliceCheck before you buy

Steps

  1. Step 1 of 8

    Isolate and restrain

    Lower attachments; engine off, key out, isolator off; lock, tag, prove dead and crib.

    Isolate upstream feeds; restrain belt travel and relieve stored drive pressure.

    Lockout kit, Rated cribbing and restraints

  2. Step 2 of 8

    Expose cooled pulley

    After smoke and heat cease, remove the tail guard and retain its fasteners.

    Socket and spanner set, Fire extinguisher

  3. Step 3 of 8

    Release belt tension

    Record take-up positions; unlock nuts and back both screws evenly to release tension.

    Keep restraints fitted; stored belt tension can eject the rock.

    Socket and spanner set, Straightedge and tape

  4. Step 4 of 8

    Extract trapped rock

    From outside the release path, pry the loose rock free without levering on the belt.

    Keep hands out of nips; stop if the rock remains loaded.

    Pry bar

  5. Step 5 of 8

    Inspect jam damage

    Check belt, splice, cogs, shaft and bearings; replace damaged parts before proceeding.

    Stop for charred rubber, exposed cords, seized bearings or bent components.

    Inspection light

  6. Step 6 of 8

    Square and tension

    Square the tail shaft, tension both sides to MSI procedure and secure the locknuts.

    Belt tension and fasteners: Check MSI serial-specific manual for tension method and Check it against your manual.

    Socket and spanner set, Straightedge and tape, Belt tension gauge, Torque wrench

  7. Step 7 of 8

    Restore guarding

    Refit the guard and all fasteners; verify clearance and clear tools from the conveyor.

    Socket and spanner set, Torque wrench

  8. Step 8 of 8

    Controlled test run

    Clear personnel; release LOTO by procedure, test empty then loaded; watch tracking.

    Stop for slip, heat or mistracking; re-isolate before any adjustment.

Stuck on this one? Snap your machine and ask Mechy. It redraws these steps for what you have in front of you.